NAVY FEDERAL CREDIT UNION – GUAM BRANCH RENOVATION

PROJECT DESCRIPTION:

On August 23, 2017 Black Construction Corporation (BCC) received the official notice of award from the Navy Federal Credit Union for the renovation of their facility at Naval Base, Guam.  Notice to Proceed was issued on August 24, 2017 with a contract completion date of January 17, 2018. 

The original scope of work consisted of the remodel of an existing and operating Navy Federal Credit Union branch. Work was divided into four phases to minimize disruption and provide access to restrooms at all times.

The renovation was carefully sequenced to ensure that credit union operations were functional throughout the entire construction period. A temporary teller line constructed at the project onset commencement assured the financial needs of our servicemen were never inconvenienced. Owner-initiated change orders were added to the original scope of work during the construction phase which included re-painting of all existing wood doors, trims and millwork. Working with our painting subcontractor, Black suggested low VOC paints to assure a safe environment for the staff and customers. Additional changes included

additional cabinets and millwork, replacement of existing exhaust fans, and installation of a new surveillance camera enclosures, power and data outlets.

A ribbon cutting and open house were held on March 18, 2018.

Size of Project:

Single Story Building with a total 6,575 sf floor area consisting of:

  • Reception and Greeter
  • Four transaction station Teller Line
  • Vault Room
  • IT/COMM Room
  • Front of and Back of House Restroom Facilities
  • 7 Managers Offices
Owner: Navy Federal Credit Union  
Contract No.: None  
Original Contract Amount: $537,808.00  
Final Contract Amount: $554,147.14  
Original Contract Completion Date: February 02, 2018  
Final Contract Completion Date: January 31, 2018  
Start Date: September 18, 2017  
Was Offeror Prime Contractor or Subcontractor: Prime
Percentage of Work Performed: 92%  
Liquidated Damages Assessed: None  
Project Manager: Bruce R. Johnson  
Job-Site Superintendent: Robert Dela Cruz  
Customer Evaluation: None