Tenant Improvement
Location:
DFS Galleria, Tumon, GuamOriginal Contract Amount:
$407,000.00Final Contract Amount:
$434,680.00Actual Date Contract Accepted:
03 March 2006Start Date:
19 December 2005Original Contract Completion:
28 February 2006Final Contract Completion:
03 March 2006Liquidated Damages Assessed:
NonePercentage of Work Performed:
Prime Contractor - 90%Project Manager:
Joselito O. GutierrezJob-site Superintendent:
Gildegardo N. NonesQuality Control Manager:
Joselito O. GutierrezArmani Fit-out Project, DFS Galleria - Guam
PROJECT DESCRIPTION:
This project involved the demolition of existing retail space and installation of new walls,partitions, store fronts and display shelves. BCC installed stainless steel ceiling, special wall finishes and floor covering. Also included in the scope was the installation of special light fixtures as well as an AC System and Fire Protection System. Most of the work activities were completed at night in order to minimize incoveniences to the store during normal store hours. The existing space was ultimately converted to Emporio Armani (1st on Guam).
Significant challenges experienced on this project
Owner furnished materials did not arrive on time. OFCI and long lead items had to be brought to Guam first, before starting the job.