Mechanical
Type of Construction :
Electrical-CommercialSize of Project:
$578,000.00Length of Project:
February 19, 2002 – August 16, 2002Percentage of
Work Self-performed:
52%
Customer Evaluation:
"Outstanding"Project Team Members
OwnerGuam International Airport Authority
Contract Administrator
EMCE Consulting Engineers
Architectural
Taniguchi Ruth & Associates
Structural
GK2 Inc. Consulting Engineers
Mechanical
EMC2 Mechanical, Inc
Electrical
EMCE Consulting Engineers
Subcontractors
Fire Alarm and Suppression SystemPacific Security Alarm
Painting
Four N Painting Company
Guam Contractors Association
2002 Excellence in
Construction Awards
Mechanical-Commercial
Under $2M-Category Winner
Jacobs Chiller Plant
PROJECT DESCRIPTION:

Main Argon and Foam Fire Alarm and Release Panel
Argon Selector Valves
Argon pneumatic operated release mechanism
Argon bottles attached to piping manifold


Argon discharge nozzle
This project was awarded to Black Construction Corporation through the competitive bidding process at a total contract amount of $578,000 with contract duration of 180 calendar days. The contract required renovation work (architectural and structural), but the major elements of the project was required upgrade of the fire detection, alarm and suppression system in the three main electrical rooms and the fuel oil (JP-4) day tank located at the generator room area.
The fire detection system in the electrical rooms consisted of two cross zoned smoke detectors installed in the protected area that, when activated, sends a signal to the fire alarm panel and triggers the fire suppression system’s release of damp Argon in the electrical rooms. Argon fire suppression system is a clean, clear and odorless inert gas that displaces oxygen inside the room to extinguish the fire.
The fire detection system in the day tank area consisted of two cross zoned flame detectors that triggers the release of the fire suppression system’s AFFF foam through a deluge valve on the main sprinkler riser.
Other works performed on this project include the following:
- Installation of a 5-ton roof top packaged air conditioning unit
- Installation of an 8,400 cfm in-line exhaust fan and ductwork at the generator room area
- Erection of a concrete air well for the generator exhaust system
- Erection of a gypsum board enclosure and provision of air conditioning for the existing generator control panel
- Erection of glass blocks at the East and West electrical rooms