PROJECT DESCRIPTION:
In April of 2003, the US Embassy Manila Facility Upgrade project was completed. The project included the facility upgrade of both the seafront compound and the chancery compound. The listing below is provided to further enumerate the scope of work.
Seafront Compound
- Demolition of old CAC
- Construction of NEW CAC
- Demolition of old perimeter fence and construction of new
- Laying/casting of lighting and security duct bank
Chancery Compound
- Demolition of old CAC
- Construction of NEW Main CAC and Consular Pedestrian CAC
- Demolition of old perimeter fence and construction of new
- Laying/casting of lighting and security duct bank
- Retroit of Portion of Chancery
- Replacement of Chancery Doors