Black Construction Corporation

International

Contracting Officers:

James Robinson
FMO/OBO, Manila
William Barnhart
FMO/OBO, Manila
John Steinbeck
OBO Washington

Final Contract Amount:

$ 1,475,000.00

Contract Completion Date:

April 15, 2003

Contract Completion Date:

April 15, 2003

Type of Contract :

Lump Sum

Start Date:

February 28, 2002

US Embassy Manila Facility Upgrade - Philippines

PROJECT DESCRIPTION:

  • US Embassy Manila
  • US Embassy Manila
  • US Embassy Manila
  • US Embassy Manila

In April of 2003, the US Embassy Manila Facility Upgrade project was completed. The project included the facility upgrade of both the seafront compound and the chancery compound. The listing below is provided to further enumerate the scope of work.

Seafront Compound

  1. Demolition of old CAC
  2. Construction of NEW CAC
  3. Demolition of old perimeter fence and construction of new
  4. Laying/casting of lighting and security duct bank

Chancery Compound

  1. Demolition of old CAC
  2. Construction of NEW Main CAC and Consular Pedestrian CAC
  3. Demolition of old perimeter fence and construction of new
  4. Laying/casting of lighting and security duct bank
  5. Retroit of Portion of Chancery
  6. Replacement of Chancery Doors