Black Construction Corporation

International

Contract No.:

N/A

Original Contract Amount:

$ 654,715.00

Final Contract Amount:

$ 654,715.00

Actual Date Contract
Accepted :

2002 February

Start Date:

2002 February

Original Contract
Completion:

2002 May

Final Contract
Completion:

2003 May

Percentage of Work Performed:

100%

Embassy of Switzerland Manila - Philippines

PROJECT DESCRIPTION:

  • Embassy of Switzerland Manila
  • Embassy of Switzerland Manila
  • Embassy of Switzerland Manila
  • Embassy of Switzerland Manila

The project called for the high end full architectural fit-out of a 1,245 square meter area. Electronic bulletproof doors, walls and glass were supplied as well as security card readers and automatic door openers. The project also required the supply and installation of high quality computer network cabling, a high end PABX phone system and an integrated security system. The construction of the mechanical, electrical and plumbing services was also undertaken by Black.